Crossrail will not open until at least 2021, incurring a further cost overrun that will take the total price of the London rail link to more than £18bn, Transport for London (TfL) has announced.
The latest assessment for the opening of the central section has ruled out late 2020 and the aim is for Crossrail to open “as soon as practically possible in 2021”, the capital’s transport authority said. TfL had previously said the Elizabeth line, as the service will be called, was unlikely to start running before 2021 but had kept an autumn 2020 opening in its plans.
The admission means that key direct services such as from Canary Wharf to Heathrow airport will almost certainly not run until at least 2022.
The latest delay was caused by the need for more time to develop signalling software and to get safety approvals for the railway.
The cost forecast for the central section of the line has risen to about £15.36bn – £400m more than the funding committed under a financing package agreed with the government. “Further modelling scenarios” suggest higher levels of risk to the project that would cost an extra £650m, TfL said.
Crossrail is Britain’s biggest infrastructure project in decades. The total cost was previously estimated at £17.6bn but has risen to as much as £18.25bn, from an initial budget of £14.8bn.
TfL said it had agreed with the Department for Transport that the financing package would stay in place and was talking to the department about how to cover the extra costs.
“TfL has been advised by Crossrail Ltd that their latest assessment is that the opening of the central section will not occur in 2020, which was the first part of the previously declared opening window,” TfL said. “The Elizabeth line will open as soon as practically possible in 2021.”
Crossrail was due to open in December 2018 but has been beset by delays and rising costs. The National Audit Office has blamed the debacle on management clinging to an unrealistic opening date instead of dealing with problems that appeared as early as 2015.
Mark Wild, the chief executive of Crossrail, said: “We are doing everything we can to complete the Elizabeth line as quickly as we can but there are no shortcuts to delivering this hugely complex railway. The Elizabeth line must be completed to the highest safety and quality standards.”
Changes to design and schedules increased costs on most of the project’s 36 main contracts. The costs of civil engineering works at Whitechapel station alone, as of December 2018, were £659m – six times the amount originally budgeted and more than double the estimate in 2015.
London politicians and business groups reacted with dismay. Caroline Pidgeon, a Liberal Democrat assembly member, said it was “appalling news for Londoners” and said both the mayor and the transport secretary had failed to hold Crossrail to account. She said the delay would also “put back further investment in London’s transport network and create further havoc to TfL’s finances. This also damages the hopes of Crossrail 2 getting started in the next decade.”
Business group London First said it was “very disappointing”. Its chief executive, Jasmine Whitbread, said: “Efforts must be redoubled to ensure that the railway opens as soon as practically possible and that we learn the lessons for future projects.”
Crossrail is on track for one impending milestone, with the full western branch out to Reading from Paddington due to come into service under TfL Rail on 15 December.